Dept. of Trans. PROGRESS Serial No. Contract No. 24-086-20-59 05-0N73U4 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 05-SB-101-7.3/9.6 NONE Progress payment No. 043 Payment period ending: 03-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,759,330.55 82,561.79 2. a. Extra Work 4,314,253.57 10,651.90 b. Adustment Comp. 718,841.55 -296,532.62 3. Materials on Hand 4. Earned Subject to Retention 91,792,425.67 -203,318.93 5. Mobilization 10,071,198.00 0.00 6. Total Work Completed 101,863,623.67 7. Deductions -186,189.67 241,985.03 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 101,677,434.00 38,666.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,666.10