Dept. of Trans. PROGRESS Serial No. Contract No. 23-331-18-25 05-0N74U4 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 18% Location: Federal Project: 05-SB-101-9.7/10.6 ACNH-Q101(420) Progress payment No. 005 Payment period ending: 11-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,710,664.40 868,173.73 2. a. Extra Work 49,079.52 49,079.52 b. Adustment Comp. 3. Materials on Hand 0.00 -28,179.00 4. Earned Subject to Retention 2,759,743.92 889,074.25 5. Mobilization 1,676,392.08 1,676,392.08 6. Total Work Completed 4,436,136.00 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,434,136.00 2,563,466.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,563,466.33