Dept. of Trans. PROGRESS Serial No. Contract No. 24-149-13-45 05-0N74U4 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 58% Location: Federal Project: 05-SB-101-9.7/10.6 ACNH-Q101(420) Progress payment No. 010 Payment period ending: 05-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,117,527.27 2,463,269.82 2. a. Extra Work 518,558.50 173,407.44 b. Adustment Comp. 10,555.60 0.00 3. Materials on Hand 219,455.00 0.00 4. Earned Subject to Retention 12,866,096.37 2,636,677.26 5. Mobilization 3,185,144.94 0.00 6. Total Work Completed 15,831,786.31 7. Deductions -22,891.00 -22,891.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,028,350.31 2,613,786.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,613,786.26