Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-13-01 05-0N74U4 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 74% Location: Federal Project: 05-SB-101-9.7/10.6 ACNH-Q101(420) Progress payment No. 028 Payment period ending: 11-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,958,691.03 1,049,465.32 2. a. Extra Work 2,055,503.63 157,854.26 b. Adustment Comp. 109,656.77 -3,351.25 3. Materials on Hand 116,725.69 0.00 4. Earned Subject to Retention 41,240,577.12 1,203,968.33 5. Mobilization 3,352,784.15 0.00 6. Total Work Completed 44,476,635.58 7. Deductions -2,891.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 44,590,470.27 1,203,968.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,203,968.33