Dept. of Trans. PROGRESS Serial No. Contract No. 24-234-10-10 05-0N74V4 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 5% Location: Federal Project: 05-SB-101-9.2/9.7 ACNH-Q101(426) Progress payment No. 002 Payment period ending: 08-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,346,480.64 2,589,300.46 2. a. Extra Work 35,109.79 35,109.79 b. Adustment Comp. 3. Materials on Hand 531,351.51 531,351.51 4. Earned Subject to Retention 3,912,941.94 3,155,761.76 5. Mobilization 3,191,050.00 3,191,050.00 6. Total Work Completed 6,572,640.43 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,103,991.94 6,346,811.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,346,811.76