Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-11-28 05-0N74V4 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 9% Location: Federal Project: 05-SB-101-9.2/9.7 ACNH-Q101(426) Progress payment No. 003 Payment period ending: 09-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,600,477.26 4,253,996.62 2. a. Extra Work 55,193.42 20,083.63 b. Adustment Comp. 3. Materials on Hand 488,047.21 -43,304.30 4. Earned Subject to Retention 8,143,717.89 4,230,775.95 5. Mobilization 4,786,575.00 1,595,525.00 6. Total Work Completed 12,442,245.68 7. Deductions -4,130.00 -4,130.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,926,162.89 5,822,170.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,822,170.95