Dept. of Trans. PROGRESS Serial No. Contract No. 24-359-07-34 05-0N74V4 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 19% Location: Federal Project: 05-SB-101-9.2/9.7 ACNH-Q101(426) Progress payment No. 006 Payment period ending: 12-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,183,594.44 2,068,154.21 2. a. Extra Work 323,770.41 229,473.25 b. Adustment Comp. 3. Materials on Hand 2,785,751.03 381,114.50 4. Earned Subject to Retention 16,293,115.88 2,678,741.96 5. Mobilization 6,062,995.00 0.00 6. Total Work Completed 19,570,359.85 7. Deductions -104,130.00 -60,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,251,980.88 2,618,741.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,618,741.96