Dept. of Trans. PROGRESS Serial No. Contract No. 25-021-09-29 05-0N74V4 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 22% Location: Federal Project: 05-SB-101-9.2/9.7 ACNH-Q101(426) Progress payment No. 007 Payment period ending: 01-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,499,796.65 2,316,202.21 2. a. Extra Work 408,336.37 84,565.96 b. Adustment Comp. 3. Materials on Hand 1,598,071.68 -1,187,679.35 4. Earned Subject to Retention 17,506,204.70 1,213,088.82 5. Mobilization 6,062,995.00 0.00 6. Total Work Completed 21,971,128.02 7. Deductions -64,130.00 40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,505,069.70 1,253,088.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,253,088.82