Dept. of Trans. PROGRESS Serial No. Contract No. 25-169-08-03 05-0N74V4 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 38% Location: Federal Project: 05-SB-101-9.2/9.7 ACNH-Q101(426) Progress payment No. 013 Payment period ending: 06-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,190,250.55 1,745,051.60 2. a. Extra Work 2,307,392.98 70,943.86 b. Adustment Comp. 3. Materials on Hand 1,808,336.89 -0.78 4. Earned Subject to Retention 28,305,980.42 1,815,994.68 5. Mobilization 6,062,995.00 0.00 6. Total Work Completed 32,560,638.53 7. Deductions -4,130.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,364,845.42 1,815,994.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,815,994.68