Dept. of Trans. PROGRESS Serial No. Contract No. 25-357-09-00 05-0N74V4 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 59% Location: Federal Project: 05-SB-101-9.2/9.7 ACNH-Q101(426) Progress payment No. 019 Payment period ending: 12-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,874,574.79 3,200,699.98 2. a. Extra Work 3,196,004.47 17,178.53 b. Adustment Comp. 3. Materials on Hand 685,962.64 -540,629.30 4. Earned Subject to Retention 40,756,541.90 2,677,249.21 5. Mobilization 6,382,100.00 0.00 6. Total Work Completed 46,452,679.26 7. Deductions -4,130.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,134,511.90 2,677,249.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,677,249.21