Dept. of Trans. PROGRESS Serial No. Contract No. 26-021-09-18 05-0N74V4 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 62% Location: Federal Project: 05-SB-101-9.2/9.7 ACNH-Q101(426) Progress payment No. 020 Payment period ending: 01-20-26 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,556,425.83 1,681,851.04 2. a. Extra Work 3,244,432.49 48,428.02 b. Adustment Comp. 3. Materials on Hand 333,797.80 -352,164.84 4. Earned Subject to Retention 42,134,656.12 1,378,114.22 5. Mobilization 6,382,100.00 0.00 6. Total Work Completed 48,182,958.32 7. Deductions -4,130.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,512,626.12 1,378,114.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,378,114.22