Dept. of Trans. FINAL Serial No. Contract No. 07-241-13-43 05-0N8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SLO-46-7.8/15.1 Federal Project: ACST-3950(4) P-3950(4) ACST-3951(5) Progress payment No. 05 Payment period ending: 07-03-07 UNION ASPHALT INC P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,765,913.27 0.00 2.a. Extra Work 42,222.28 376.68 b. Adjustment Comp. -10,089.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,798,046.31 376.68 5. Mobilization 6. Total Work Completed 2,798,046.31 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,798,046.31 376.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 376.68