Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-290-17-11 05-0P0904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-MON-218-R0.0/2.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-06-08 INTERMOUNTAIN SLURRY SEAL INC P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 524,010.50 0.00 2.a. Extra Work 39,030.24 35,974.21 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 563,040.74 35,974.21 5. Mobilization 6. Total Work Completed 563,040.74 7. Deductions 0.00 9,205.41 8. a.Contract Retentions -21,597.82 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 21,597.82 0.00 9. Total pay to Contractor 563,040.74 45,179.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,179.62