Dept. of Trans. PROGRESS Serial No. Contract No. 07-054-10-30 05-0P1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 31% 05-SB-101-26.9/26.9 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-07 SPECIALTY CONSTRUCTION INC 645 CLARION COURT SAN LUIS OBISPO CA 93401 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 214,482.87 74,804.54 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 214,482.87 74,804.54 5. Mobilization 90,250.00 0.00 6. Total Work Completed 304,732.87 7. Deductions -27,343.37 0.00 8. a.Contract Retentions -11,446.94 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 265,942.56 74,804.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,804.54