Dept. of Trans. PROGRESS Serial No. Contract No. 08-143-11-06 05-0P2904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 58% 05-SLO-166-16.5/16.5 Federal Project: NONE Progress payment No. 07 Payment period ending: 05-20-08 ABHE AND SVOBODA INC P O BOX 251 PRIOR LAKE MN 55372 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 889,685.10 424,306.12 2.a. Extra Work 12,613.08 2,616.73 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 902,298.18 426,922.85 5. Mobilization 264,413.50 55,666.00 6. Total Work Completed 1,166,711.68 7. Deductions 8. a.Contract Retentions -51,159.65 -3,622.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,115,552.03 478,966.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 478,966.73