Dept. of Trans. PROGRESS Serial No. Contract No. 10-025-12-57 05-0P3404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 58% 05-MON-1-26.1/26.1 Federal Project: ER-43G8(4) Progress payment No. 05 Payment period ending: 01-20-10 CALEX ENGINEERING COMPANY 23651 PINE STREET NEWHALL CA 91321 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 428,125.60 67,927.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 428,125.60 67,927.00 5. Mobilization 95,000.00 20,000.00 6. Total Work Completed 523,125.60 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 523,125.60 87,927.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,927.00