Dept. of Trans. PROGRESS Serial No. Contract No. 06-249-14-11 05-0P5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 75% 05-MON-218-1.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-07-06 MONTEREY PENINSULA ENGINEERING P. O. BOX 2317 MONTEREY, CA 93942 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,320.00 2,320.00 2.a. Extra Work 57,432.43 57,432.43 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 59,752.43 59,752.43 5. Mobilization 6. Total Work Completed 59,752.43 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,752.43 59,752.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,752.43