Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-323-15-49 05-0P6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SCR-9-1.8/1.8 Federal Project: ER-43J2(4) Progress payment No. 06 Payment period ending: 11-17-10 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 412,952.25 26,997.00 2.a. Extra Work 14,964.40 1,095.82 b. Adjustment Comp. -10,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 417,916.65 28,092.82 5. Mobilization 47,000.00 0.00 6. Total Work Completed 464,916.65 7. Deductions -20,000.00 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 444,916.65 8,092.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,092.82