Dept. of Trans. PROGRESS Serial No. Contract No. 11-171-12-15 05-0P9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 47% 05-SB-154-22.9/23.1 Federal Project: ARRA-P154(18) L-P154(18) Progress payment No. 05 Payment period ending: 06-20-11 BUGLER CONSTRUCTION 4847 HOPYARD ROAD STE 4 NO 39 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,008.00 42,000.00 2.a. Extra Work 74,316.90 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 181,324.90 42,000.00 5. Mobilization 47,500.00 0.00 6. Total Work Completed 228,824.90 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 228,824.90 42,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,000.00