Dept. of Trans. PROGRESS Serial No. Contract No. 13-085-07-20 05-0P9704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 100% 05-MON-68-R3.9/R10.8 Federal Project: STPP-680(22E) Progress payment No. 08 Payment period ending: 03-20-13 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,593,845.58 -15,066.50 2.a. Extra Work 88,440.81 50,230.98 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,682,286.39 35,164.48 5. Mobilization 63,000.00 0.00 6. Total Work Completed 2,745,286.39 7. Deductions -10,750.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,734,536.39 35,164.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,164.48