Dept. of Trans. PROGRESS Serial No. Contract No. 09-142-09-51 05-0Q1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 45% 05-SLO-166-17.8/17.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-20-09 JEFFCO PAINTING AND COATING INC P O BOX 2015 VALLEJO CA 94592 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,200.00 860.00 2.a. Extra Work 18,443.10 18,443.10 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 24,643.10 19,303.10 5. Mobilization 8,650.00 8,650.00 6. Total Work Completed 33,293.10 7. Deductions 8. a.Contract Retentions -2,464.31 -1,930.31 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,828.79 26,022.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,022.79