Dept. of Trans. PROGRESS Serial No. Contract No. 09-021-15-09 05-0Q1904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 72% 05-SLO-1-52.9/52.9 Federal Project: 05-SLO-1-R59.8/R59.8 NONE 05-SLO-1-R66.8/R66.8 Progress payment No. 03 Payment period ending: 01-20-09 DEBRUIN CONSTRUCTION INC P O BOX 1355 FRENCH CAMP CA 95231 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 222,190.82 90,562.54 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 222,190.82 90,562.54 5. Mobilization 18,000.00 0.00 6. Total Work Completed 240,190.82 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -11,109.54 -4,528.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 228,081.28 86,034.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 86,034.41