Dept. of Trans. PROGRESS Serial No. Contract No. 10-235-17-13 05-0Q2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-MON-101-R12.6/R15.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 08-20-10 SOUZA CONSTRUCTION INC P O BOX 3810 SAN LUIS OBISPO CA 934033810 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 563,747.49 653.20 2.a. Extra Work 8,965.34 0.00 b. Adjustment Comp. -102.80 0.00 3. Materials on Hand 4. Earned Subject to Retention 572,610.03 653.20 5. Mobilization 6. Total Work Completed 572,610.03 7. Deductions -11,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 561,610.03 653.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 653.20