Dept. of Trans. PROGRESS Serial No. Contract No. 11-206-09-26 05-0Q5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 16% 05-MON-101-53.1/53.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 07-20-11 DREAMBUILDER 1361 E GARTEN DRIVE PLACENTIA CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 327,250.08 32,492.00 2.a. Extra Work 4,858.06 4,858.06 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 332,108.14 37,350.06 5. Mobilization 6. Total Work Completed 332,108.14 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 332,108.14 37,350.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 37,350.06