Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-157-09-17 05-0Q5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-MON-101-53.1/53.9 Federal Project: NONE Progress payment No. 09 Payment period ending: 02-29-12 DREAMBUILDER 1324 LAWSON LN PLACENTIA, CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 351,168.14 0.00 2.a. Extra Work 56,528.22 28,830.96 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 407,696.36 28,830.96 5. Mobilization 6. Total Work Completed 407,696.36 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 397,696.36 28,830.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,830.96