Dept. of Trans. PROGRESS Serial No. Contract No. 15-112-13-47 05-0Q5904 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 35% Location: Federal Project: 05-SCR-9-3.8/18.7 STP-S009(20) Progress payment No. 003 Payment period ending: 04-20-15 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 356,535.50 154,238.50 2. a. Extra Work 9,748.29 5,618.29 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 366,283.79 159,856.79 5. Mobilization 67,500.00 0.00 6. Total Work Completed 433,783.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 433,783.79 159,856.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 159,856.79