Dept. of Trans. PROGRESS Serial No. Contract No. 17-234-10-36 05-0Q6004 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 5% Location: Federal Project: 05-SCR-17-0.7/1.4 ACNH-PP01-7(112) Progress payment No. 005 Payment period ending: 08-20-17 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 519,500.15 245,439.95 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 126,141.98 126,141.98 4. Earned Subject to Retention 645,642.13 371,581.93 5. Mobilization 297,675.00 99,225.00 6. Total Work Completed 817,175.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 943,317.13 470,806.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 470,806.93