Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-07-20 05-0Q6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 31% 05-SLO-101-7.8/12.5 Federal Project: ACNH-GQ10(122) Progress payment No. 02 Payment period ending: 10-20-12 CALPORTLAND COSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 649,929.42 464,450.44 2.a. Extra Work 23,827.91 23,827.91 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 673,757.33 488,278.35 5. Mobilization 76,000.00 36,000.00 6. Total Work Completed 749,757.33 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 749,757.33 524,278.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 524,278.35