Dept. of Trans. PROGRESS Serial No. Contract No. 11-111-12-48 05-0Q6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 8% 05-SLO-101-55.8/57.9 Federal Project: HSNH-Q101(190) G-Q101(190) Progress payment No. 03 Payment period ending: 04-20-11 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 150,816.20 74,841.40 2.a. Extra Work 18,037.38 8,257.51 b. Adjustment Comp. -11,025.00 -9,375.00 3. Materials on Hand 4. Earned Subject to Retention 157,828.58 73,723.91 5. Mobilization 54,000.00 54,000.00 6. Total Work Completed 211,828.58 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 211,828.58 127,723.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 127,723.91