Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-13-38 05-0Q6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 28% 05-SLO-101-55.8/57.9 Federal Project: HSNH-Q101(190) G-Q101(190) Progress payment No. 07 Payment period ending: 08-20-11 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,867,790.58 346,843.50 2.a. Extra Work 136,870.53 15,077.76 b. Adjustment Comp. 5,771.92 -3,399.00 3. Materials on Hand 4. Earned Subject to Retention 2,010,433.03 358,522.26 5. Mobilization 108,000.00 0.00 6. Total Work Completed 2,118,433.03 7. Deductions -1,750.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,116,683.03 358,522.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 358,522.26