Dept. of Trans. PROGRESS Serial No. Contract No. 10-144-16-45 05-0Q6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 12% 05-SB-101-82.1/84.3 Federal Project: ACHS-Q101(163) NHG-Q101(163) Progress payment No. 01 Payment period ending: 05-20-10 GRANITE CONSTRUCTION COMPANY 585 WEST BEACH STREET WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,737.70 23,737.70 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 23,737.70 23,737.70 5. Mobilization 6. Total Work Completed 23,737.70 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,737.70 23,737.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,737.70