Dept. of Trans. PROGRESS Serial No. Contract No. 10-201-14-24 05-0Q6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 49% 05-SB-101-82.1/84.3 Federal Project: ACHS-Q101(163) NHG-Q101(163) Progress payment No. 03 Payment period ending: 07-20-10 GRANITE CONSTRUCTION COMPANY 585 WEST BEACH STREET WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 342,994.73 222,393.23 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 342,994.73 222,393.23 5. Mobilization 118,750.00 56,250.00 6. Total Work Completed 461,744.73 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 461,744.73 278,643.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 278,643.23