Dept. of Trans. PROGRESS Serial No. Contract No. 10-055-10-08 05-0Q6604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 10% 05-SB-135-R10.4/11.7 Federal Project: HSNH-S135(7) G-S135(7) Progress payment No. 02 Payment period ending: 02-20-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,951.95 19,659.63 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 23,951.95 19,659.63 5. Mobilization 6. Total Work Completed 23,951.95 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,951.95 19,659.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,659.63