Dept. of Trans. PROGRESS Serial No. Contract No. 11-171-11-09 05-0R2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 45% 05-MON-101-86.6/R87.7 Federal Project: ACNH-Q101(191) Progress payment No. 02 Payment period ending: 06-20-11 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014820 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,535.00 20,645.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 66,332.17 66,332.17 4. Earned Subject to Retention 88,867.17 86,977.17 5. Mobilization 50,250.00 50,250.00 6. Total Work Completed 72,785.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 139,117.17 137,227.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 137,227.17