Dept. of Trans. PROGRESS Serial No. Contract No. 16-202-09-40 05-0R5104 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 100% Location: Federal Project: 05-SCR-1 STP-000C(400) 05-MON-1 Progress payment No. 009 Payment period ending: 07-20-16 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 879,355.71 625.00 2. a. Extra Work 9,383.80 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 888,739.51 625.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 988,739.51 7. Deductions -92,803.72 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 895,935.79 625.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 625.00