Dept. of Trans. PROGRESS Serial No. Contract No. 16-295-10-42 05-0R5104 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 82% Location: Federal Project: 05-SCR-1 STP-000C(400) 05-MON-1 Progress payment No. 011 Payment period ending: 10-20-16 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 879,355.71 0.00 2. a. Extra Work 16,865.29 7,481.49 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 896,221.00 7,481.49 5. Mobilization 100,000.00 0.00 6. Total Work Completed 996,221.00 7. Deductions -2,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 993,721.00 7,481.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,481.49