Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-12-22 05-0R7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 94% 05-SLO-101-58.9/63.6 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-20-09 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISOM BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,853,403.11 983,551.35 2.a. Extra Work b. Adjustment Comp. -2,959.65 -13,490.67 3. Materials on Hand 4. Earned Subject to Retention 1,850,443.46 970,060.68 5. Mobilization 6. Total Work Completed 1,850,443.46 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,850,443.46 970,060.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 970,060.68