Dept. of Trans. FINAL Serial No. Contract No. 13-276-09-10 05-0R8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-MON-1-0.3/ .0 Federal Project: ACST-PP00-1(156 Progress payment No. 16 Payment period ending: 07-23-13 SOUZA CONSTRUCTION INC P O BOX 3810 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 317,616.60 0.00 2.a. Extra Work 12,576.59 0.00 b. Adjustment Comp. -1,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 328,693.19 0.00 5. Mobilization 19,750.00 0.00 6. Total Work Completed 348,443.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 348,443.19 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00