Dept. of Trans. SEMI-FINAL Serial No. Contract No. 13-241-09-09 05-0R8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SBT-25-0.0/ .0 Federal Project: 05-MON-101-0.0/ .0 NONE 05-MON-183-0.0/ .0 Progress payment No. 10 Payment period ending: 06-17-13 BROUGH CONSTRUCTION INC 634 PRINTZ ROAD ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 493,405.68 0.00 2.a. Extra Work 165,266.43 13,077.55 b. Adjustment Comp. -25,520.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 633,152.11 13,077.55 5. Mobilization 40,000.00 0.00 6. Total Work Completed 673,152.11 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 673,152.11 23,077.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,077.55