Dept. of Trans. PROGRESS Serial No. Contract No. 10-323-14-25 05-0R8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 78% 05-MON-101-R41.3/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-10 SANTA MARGARITA CONSTRUCTION CORP P O BOX 357 TEMPLETON CA 93465 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 727,320.21 296,463.52 2.a. Extra Work 117,103.90 117,103.90 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 844,424.11 413,567.42 5. Mobilization 118,085.00 0.00 6. Total Work Completed 962,509.11 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -41,356.74 -41,356.74 c. Reduction after 95% Comp. 9. Total pay to Contractor 920,152.37 372,210.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 372,210.68