Dept. of Trans. PROGRESS Serial No. Contract No. 14-203-13-06 05-0R9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 27% 05-SCR-1-9.7/17.6 Federal Project: SNHG-P001(578) Progress payment No. 03 Payment period ending: 07-20-14 RGW CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 384,869.06 122,637.20 2.a. Extra Work 95,189.00 0.00 b. Adjustment Comp. 55,635.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 535,693.56 122,637.20 5. Mobilization 162,355.00 0.00 6. Total Work Completed 698,048.56 7. Deductions -30,659.30 -30,659.30 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 667,389.26 91,977.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 91,977.90