Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-177-12-33 05-0S0304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-1-0.0 STP-X083(18) 05-SB-101-0.0 05-SB-192-0.0 Progress payment No. 006 Payment period ending: 06-15-15 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 264,722.80 14,907.75 2. a. Extra Work 40,503.33 37,018.27 b. Adustment Comp. -21,681.00 -21,681.00 3. Materials on Hand 4. Earned Subject to Retention 283,545.13 30,245.02 5. Mobilization 32,030.00 0.00 6. Total Work Completed 315,575.13 7. Deductions -20,000.00 -19,776.10 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 295,575.13 10,468.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,468.92