Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-011-09-45 05-0S0304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-1-0.0 STP-X083(18) 05-SB-101-0.0 05-SB-192-0.0 Progress payment No. 008 Payment period ending: 06-15-15 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 281,301.80 16,579.00 2. a. Extra Work 40,503.33 0.00 b. Adustment Comp. -2,900.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 318,905.13 16,579.00 5. Mobilization 32,030.00 0.00 6. Total Work Completed 350,935.13 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 340,935.13 26,579.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,579.00