Dept. of Trans. PROGRESS Serial No. Contract No. 10-355-13-48 05-0S2104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 05-SB-1-R23.3/M29.9 Federal Project: SARR-P001(545) A-P001(545) Progress payment No. 05 Payment period ending: 12-20-10 VALLEY SLURRY SEAL COMPANY P O BOX 981330 WEST SACRAMENTO CA 95798 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,404,309.99 77,318.55 2.a. Extra Work b. Adjustment Comp. -5,569.45 -5,569.45 3. Materials on Hand 4. Earned Subject to Retention 1,398,740.54 71,749.10 5. Mobilization 6. Total Work Completed 1,398,740.54 7. Deductions -3,500.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,395,240.54 70,749.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,749.10