Dept. of Trans. PROGRESS Serial No. Contract No. 10-299-13-15 05-0S2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 83% 05-SB-154-23.3/32.3 Federal Project: SARR-P154(19) A-P154(19) Progress payment No. 04 Payment period ending: 10-20-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,489,788.54 104,625.00 2.a. Extra Work 67,565.85 5,828.97 b. Adjustment Comp. 34,936.13 -24,804.37 3. Materials on Hand 4. Earned Subject to Retention 1,592,290.52 85,649.60 5. Mobilization 6. Total Work Completed 1,592,290.52 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,592,290.52 85,649.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,649.60