Dept. of Trans. PROGRESS Serial No. Contract No. 10-323-14-25 05-0S4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 75% 05-SB-246-9.6/R21.0 Federal Project: ACHS-P246(15) STP-P246(15) Progress payment No. 03 Payment period ending: 11-20-10 R BURKE CORPORATION P O BOX 957 SAN LUIS OBISPO CA 93406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 659,684.14 140,901.63 2.a. Extra Work 9,455.18 9,455.18 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 669,139.32 150,356.81 5. Mobilization 23,000.00 0.00 6. Total Work Completed 692,139.32 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 692,139.32 150,356.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 150,356.81