Dept. of Trans. PROGRESS Serial No. Contract No. 11-080-10-21 05-0S6104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 45% 05-SB-101-12.7/20.9 Federal Project: ACHN-Q101(174) Progress payment No. 09 Payment period ending: 03-20-11 GEORGE REED INC P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,379,443.18 712.50 2.a. Extra Work 125,043.37 77,118.73 b. Adjustment Comp. -2,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,502,486.55 77,831.23 5. Mobilization 140,000.00 0.00 6. Total Work Completed 3,642,486.55 7. Deductions -2,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,639,986.55 77,831.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,831.23