Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-283-11-15 05-0S6104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SB-101-12.7/20.9 Federal Project: ACHN-Q101(174) Progress payment No. 15 Payment period ending: 07-14-11 GEORGE REED INC P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,984,830.86 712.50 2.a. Extra Work 197,857.76 19,443.77 b. Adjustment Comp. 38,442.96 -1,013.04 3. Materials on Hand 4. Earned Subject to Retention 6,221,131.58 19,143.23 5. Mobilization 140,000.00 0.00 6. Total Work Completed 6,361,131.58 7. Deductions -22,500.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,338,631.58 39,143.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,143.23