Dept. of Trans. PROGRESS Serial No. Contract No. 10-293-15-35 05-0S6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 53% 05-SLO-46-29.9/31.1 Federal Project: 05-SLO-46-31.4/32.0 ACNH-P046(44) Progress payment No. 02 Payment period ending: 10-20-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 615,565.40 48,524.82 2.a. Extra Work 1,650.00 1,650.00 b. Adjustment Comp. -4,026.37 -4,026.37 3. Materials on Hand 4. Earned Subject to Retention 613,189.03 46,148.45 5. Mobilization 6. Total Work Completed 613,189.03 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 613,189.03 46,148.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,148.45