Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-026-14-01 05-0S6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SLO-46-29.9/31.1 Federal Project: 05-SLO-46-31.4/32.0 ACNH-P046(44) Progress payment No. 04 Payment period ending: 01-20-11 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 671,258.85 25,320.85 2.a. Extra Work 1,650.00 0.00 b. Adjustment Comp. -4,026.37 0.00 3. Materials on Hand 4. Earned Subject to Retention 668,882.48 25,320.85 5. Mobilization 6. Total Work Completed 668,882.48 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 658,882.48 15,320.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,320.85